PROJECT OVERVIEW

Project Timeline

 

We have surpassed the halfway mark in construction of the North Tarrant Express' 13.5-mile corridor, which is anticipated to be completed in June 2015. This marks an important milestone for the project and signals the beginning of future traffic relief for the North Fort Worth and Northeast Tarrant County areas.

As a result, road work will likely affect traffic conditions during your daily commute, so we encourage you to check back regularly for updates on the construction schedule as well as current and upcoming lane closures.

The project timeline information below will be updated on a monthly basis, typically following the monthly project team construction meeting, which takes place on the first or second Friday of each month.

For a map of current and upcoming construction activity, please click here.

 

What Can You Expect in the Coming Weeks?

 
IH 35W/IH 820 Interchange
 

Continued construction of the TEXpress managed lane tie-ins from northbound and southbound IH 35W to eastbound IH 820.

 

Construction of the eastbound and westbound IH 820 frontage roads and general purpose lanes from the interchange to Beach Street.

IH 820 at Riverside Drive
 

Continued construction of columns for the new Riverside Drive bridge over IH 820.

IH 820 near Beach Street
 

Deck panel placement and deck pouring for the new eastbound and westbound IH 820 TEXpress lanes over Beach Street.

IH 820 near Haltom Road
 

Panel placement and concrete deck pouring for the expansion of the Haltom Road bridge.

 

Continued construction of the eastbound and westbound IH 820 frontage roads from Haltom Road to Beach Street.

 

Demolition of the old Union Pacific rail bridge.

IH 820 near Denton Highway 377
 

Deck panel placement and deck pouring for the Denton Highway 377 expansion.

IH 820 between Iron Horse Blvd. and Rufe Snow Drive
 

The beginning phases for the reconstruction of the Iron Horse bridge.

 

Construction of the eastbound and westbound IH 820 frontage roads from Rufe Snow Drive to Iron Horse Blvd.

 

Construction of the new DART rail line.

IH 820 near Holiday Lane
 

Construction of the new Holiday Lane bridge.

 

Construction of the eastbound and westbound IH 820 frontage roads, general purpose lanes and TEXpress lanes from Holiday Lane to Grapevine Highway 26.

IH 820/ SH 121/ SH 183 Interchange
 

Construction of columns and caps and deck panel placement within the IH 820/SH 121/SH 183 interchange.

SH 121/183 between North East Mall and Precinct Line Rd
 

Placement of bridge panels and deck pours for new eastbound SH 121/183 lanes over Precinct Line Road.

SH 121/183 near Hurstview Drive
 

Reconstructing eastbound SH 121/183 frontage road from Hurstview Drive to Cavender Drive.

SH 121/183 near Norwood Drive
 

Partial demolition of eastbound SH 121/183 lanes over Norwood Drive.

SH 121/183 near Brown Trail
 

Continued expansion of Brown Trail.

 

Closure of the westbound SH 121/183 frontage road from Brown Trail to Norwood Drive for the summer.

SH 121/183 near Bedford Road
 

Placement of bridge panels and deck pours for new eastbound SH 121/183 lanes over Bedford Road.

SH 121/183 near Forest Ridge Drive
 

Placement of beams and bridge panels for new eastbound SH 121/183 lanes over Forest Ridge Drive.

SH 121/SH 183 Split
 

Major traffic shift of eastbound SH 121/183 lanes to the north, resulting in a temporary LEFT-LANE EXIT to northbound SH 121.

SH 183 east of SH 121/183 split
 

Construction of new ramps and the continued expansion of SH 183 from Westpark Way to Industrial Boulevard in Euless.

 
 
 
 
 
 